For your information
Proposed Temporary Road Closure – Barton Rd, Harlington
I have a request for a Temporary Road Closure at the above location to enable Carriageway Surfacing Works to go ahead in safety. Details are listed in the schedule below and having assessed the application I am satisfied the request is justified.
The alternative route for this closure is as in the details below and will be signed accordingly. The restrictions are to be in operation only when the necessary signs are erected on site. The Legal Order will be made to cover a 12 month period.
If you have any observations you wish to make I would be grateful if you could let me know as soon as possible.
Streetworks Team
……………………………………………………………………………………
Road: Barton Rd, Harlington
Application from: Ringway Jacobs OBO Central Bedfordshire Council – 03003008049
Reason: Carriageway Resurfacing
Length affected: From o/s 101 joint at T-Junction to o/s no 13
Date: This Closure is expected to take place between the dates 24th August to 1st September the hours of 0800-1800
Diversion: Head north-east on Barton Rd towards Goswell End Rd
Turn left onto Goswell End Rd
Turn left onto Westoning Rd
Turn left onto Church Rd
Church Rd turns right and becomes Barton Rd
- The applicant will be responsible for taking down all Central Bedfordshire Council public notices immediately after the works requiring the Order have been completed.