Dear Neighbour

 

Harlington Railway Station Footbridge Upgrade – October 2025

 

Further to my previous letters, I’m writing to let you know about the work near to your home in Harlington during October to replace the station footbridge.

 

Construction work started in May 2025 and is planned to finish in May 2026. We will continue to maximise the use of daytime shifts to undertake the work, however some of our activities have to be carried out when trains aren’t running because we’ll need to have staff and equipment on the track. For work on platform 1, we will need to access the worksite using Paxton Approach, access will be maintained for the residents in the locality.

 

Our team will be using a variety of equipment, including excavators, breakers, drills, circular saws, concrete pumps, generators, mixers, telehandlers and hand tools, and as a result some disturbance is unavoidable. However, every effort will be made to minimise any unnecessary noise, and those working on site are briefed on working responsibly in the local community.

We will be undertaking as much of the noisy work as possible on day shifts and will use measures such as acoustic noise barriers during night shifts to minimise the noise, using hand tools for the breaking out of material on night shifts, with saw cuts undertaken on days wherever this is possible.

The work to rebuild platforms 2 and 3 has been completed and preparatory work for the replacement of the footbridge continues to progress well on site. The augured piling work has been successfully completed on all platforms.

Day shifts will be undertaken between 07:00 and 17:00.

Night shifts

Night shift dates and times Details of work
22:00 Saturday 4 October – 09:00 Sunday 5 October – 1 x nightshift Installation of Duct Routes/ Manholes (Excavators to be used)
22:00 Saturday 11 October – 09:00 Sunday 12 October – 1 x nightshift

 

22:00 Monday 13 October – 09:00 Saturday 18 October – 5 x nightshifts

Installation of Duct Routes/ Manholes (Excavators to be used)

 

Concrete Pour to Platform 2/3.

22:00 Saturday 18 October – 09:00 Sunday 19 October – 1 x nightshift

 

22:00 Tuesday 21 October – 09:00 Saturday 25 October – 4 x nightshifts

Saturday Night Working – Installation of Duct Routes/ Manholes (Excavators to be used)

 

Midweek Nights – Brickwork Repairs (Breaker to be used)

22:00 Saturday 25 October – 09:00 Sunday 26 October – 1 x nightshift

 

22:00 Monday 27 October – 06:00 Friday 31 October – 4 x nightshifts

Saturday Night Working – Installation of Duct Routes/ Manholes (Excavators to be used)

 

Midweek Nights – Brickwork Repairs (Breaker to be used)

 

 

As I’ve previously explained, working with infrastructure of this age does mean that there could be times when we come across unexpected obstructions or unchartered buried services within the platform. This could result in the unexpected use of equipment such as a concrete breaker for a short period of time. We will try to minimise the effect of this on neighbours but may have to finish work started at night to ensure the safety of the platforms for daytime use.

 

For further information about our work which takes place on the railway please visit www.networkrail.co.uk/livingbytherailway  alternatively if you have any additional questions or concerns, please visit www.networkrail.co.uk or telephone our 24-hour National Helpline on 03457 11 41 41.